The FERC today issued Order No. 871-A, seeking further comment
on modifications last summer to its regulations under Natural Gas
Act Sections 3 and 7 that prohibited initiating pipeline
construction, pending timely filing of any rehearing request, or a
rehearing order on the merits. The Commission has requested initial
briefs promptly, by February 16, and reply briefs
by March 3. Perhaps not coincidentally, Order No.
871 is currently pending judicial review.
Order No. 871-A inquires whether the Commission should
- prohibit construction while a
rehearing request is pending, even though traditionally
construction could begin before that (i.e., following an order
authorizing construction); or