FERC Rejects MISO's Proposed Restrictions On Joining The Development Queue

Sheppard
Sheppard
Contributor
Sheppard

Sheppard

Businesses turn to Sheppard to deliver sophisticated counsel to help clients move ahead. With more...

View firm profile
Explore more from Sheppard

Securing interconnection and transmission rights and completing related upgrades is often the longest lead-time item in an electric generator's development timeline.

United StatesEnergy and Natural Resources

Securing interconnection and transmission rights and completing related upgrades is often the longest lead-time item in an electric generator's development timeline. At the same time, many potential new power plants are being developed and vying for access to the electric transmission grid. The policy of most grid operators is to address interconnection requests on a "first come first served" basis. As a result, developers/interconnection customers are incentivized to submit their interconnection requests as early in the development process as possible in order to save their projects' place in line. Over the last two years, Midcontinent Independent System Operator, Inc. ("MISO") experienced record-high interconnection requests, and yet nearly 80% of these submissions ultimately were withdrawn prior to commercial operation of the project. MISO attributed this trend to developers submitting multiple requests for the same proposed project to test (and quickly

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from