FERC Issues NOPR Proposing To Include Primary Frequency Response Provisions In Pro Forma Generation Interconnection Agreements

FERC explained that the proposed modifications are intended to address industry-wide reliability concerns related to declining frequency response performance.

United StatesEnergy and Natural Resources

On November 17, 2016, FERC issued a Notice of Proposed Rulemaking ("NOPR") in which it proposed modifications to its pro forma interconnection agreements that would require new generating facilities to install and enable primary frequency response equipment as a condition of interconnection. FERC explained that the proposed modifications are intended to address industry-wide reliability concerns related to declining frequency response performance.

In the NOPR, FERC explained that changes in the balance between growth and load causes frequency to deviate from its scheduled value of 60 Hertz. FERC stated further that deviations too far above or below 60 Hertz can threaten reliability by causing generation tripping, under frequency load shedding, or cascading outages. According to FERC, primary frequency response provided by individual generators can mitigate abnormal frequency variations through the autonomous actions of a generator's turbine governor, and other plant

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from