FERC Further Clarifies Its Orders Reforming Generator Interconnection Procedures And Agreements

On August 16, 2019, the Federal Energy Regulatory Commission ("FERC" or "the Commission") issued an order granting in part and denying in part requests for further clarification of its reform

United StatesEnergy and Natural Resources

On August 16, 2019, the Federal Energy Regulatory Commission ("FERC" or "the Commission") issued an order granting in part and denying in part requests for further clarification of its reform of Large Generator Interconnection Agreements ("LGIA") and Procedures ("LGIP").1 Order No. 845-B affirms FERC's prior findings that the expansion of an interconnection customer's option to build does not impede transmission owners' ability to recover a return of and on network upgrades. The order also reiterates FERC's determination not to revise the pro forma LGIA's indemnity provisions.

Order No. 845—FERC's Final Rule revising the pro forma LGIP and LGIA—made various reforms to "improve certainty for interconnection customers, promote more informed interconnection decisions, and enhance the interconnection process."2 Among these changes, the Commission expanded interconnection customers' ability to exercise the option to build transmission providers' interconnection

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from