On August 16, 2019, the Federal Energy Regulatory Commission
("FERC" or "the Commission") issued an order
granting in part and denying in part requests for further
clarification of its reform of Large Generator Interconnection
Agreements ("LGIA") and Procedures ("LGIP").1 Order
No. 845-B affirms FERC's prior findings that the expansion of
an interconnection customer's option to build does not impede
transmission owners' ability to recover a return of and on
network upgrades. The order also reiterates FERC's
determination not to revise the pro forma LGIA's indemnity
provisions.
Order No. 845—FERC's Final Rule revising the pro
forma LGIP and LGIA—made various reforms to
"improve certainty for interconnection customers, promote more
informed interconnection decisions, and enhance the interconnection
process."2 Among these changes, the Commission expanded
interconnection customers' ability to exercise the option to
build transmission providers' interconnection