FERC Extends Order No. 2023 Interconnection Process Reform Compliance Deadlines

Akin
Akin
Contributor
Akin

Akin

Akin is a global law firm with more than 1,100 lawyers and advisors who pride themselves on...

View firm profile
Explore more from Akin

On October 25, 2023, the Federal Energy Regulatory Commission (FERC) issued an order1 that extended the deadline for electric transmission providers to comply with its Order No. 2023...

United StatesEnergy and Natural Resources

On October 25, 2023, the Federal Energy Regulatory Commission (FERC) issued an order1 that extended the deadline for electric transmission providers to comply with its Order No. 2023, "Improvements to Generator Interconnection Procedures and Agreements" (the Final Rule2). The new compliance filing deadline is Wednesday, April 3, 2024, or 210 calendar days from the Final Rule's publication in the Federal Register on September 6, 2023. The previous deadline had been December 5, 2023, or 90 days from the publication date. The revised deadline applies to "all transmission providers, except for those with wholesale distribution access tariffs," whose compliance filings are now due "within 90 calendar days of the date on which their relevant regional transmission organization or independent systems operator submits its compliance filing."3 FERC clarified that the Extension Order "does not change or modify any other determination or other deadlines established by Order No.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from