Share on LinkedInShare on LinkedIn

ARTICLE · 03 JULY 2015

FERC Denies PSEG Complaint, Upholds PJM's Solicitation Process For The "Artificial Island"

On June 16, 2015, the Commission denied a complaint filed by Public Service Electric and Gas Company ("PSEG") against PJM Interconnection, L.L.C. ("PJM")...

United StatesEnergy and Natural Resources

On June 16, 2015, the Commission denied a complaint filed by Public Service Electric and Gas Company ("PSEG") against PJM Interconnection, L.L.C. ("PJM") in which PSEG contended that PJM did not comply with certain rules of its Open Access Transmission Tariff ("OATT") in conducting a competitive solicitation for transmission solutions to the "Artificial Island"— a term that refers to the transmission and generation infrastructure associated with a nuclear complex that includes the Salem 1, Salem 2, and Hope Creek nuclear generating units.  In denying PSEG's complaint, the Commission found that: (i) PJM was not required to follow its Order No. 1000 procedures in its Artificial Island solicitation; and (ii) PJM complied with its pre-Order No. 1000 OATT rules in conducting the solicitation.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from