The Federal Energy Regulatory Commission (FERC) issued a Final Rule on November 22 amending the pro forma Small Generator Interconnection Procedures (SGIP) and pro forma Small Generator Interconnection Agreement (SGIA).

United StatesEnergy and Natural Resources

The Federal Energy Regulatory Commission (FERC) issued a Final Rule[1] on November 22 amending the pro forma Small Generator Interconnection Procedures (SGIP) and pro forma Small Generator Interconnection Agreement (SGIA). The SGIP and SGIA govern the interconnection of Small Generating Facilities with a public utility's transmission facilities or its FERC-jurisdictional distribution facilities and apply to facilities with capacity up to 20 megawatts (MW). The SGIP and SGIA also include special "fast track" provisions for Small Generating Facilities (no larger than 2 MW) as well as inverter-based facilities up to 10 kilowatts (kW).

FERC concluded that the reforms adopted in the Final Rule will reduce the time and cost required to process small generator requests for Interconnection Customers, maintain reliability, increase energy supply, and remove barriers to the development of new distributed resources. The effective date of the Final Rule is 60 days after its

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from