ARTICLE · 15 JUNE 2017

D.C. Circuit Upholds FERC's Interpretation in TANC/PG&E Contract Dispute

The Operation Agreement coordinates the operation of three transmission lines, collectively referred to as the "California-Oregon Intertie," ...

United StatesEnergy and Natural Resources

On June 1, 2017, the United States Court of Appeals for the District of Columbia Circuit ("D.C. Circuit") denied petitions for review and upheld FERC's interpretation of a transmission agreement (the "Operation Agreement") between the Transmission Agency of Northern California ("TANC") and Pacific Gas and Electric Company ("PG&E").

The Operation Agreement coordinates the operation of three transmission lines, collectively referred to as the "California-Oregon Intertie," that deliver electricity from the Pacific Northwest to Central California.  TANC owns and manages one of these lines, while PG&E owns the largest portion of the other two.  Among other things, the Operation Agreement specified certain "remedial action schemes," which are actions that TANC and PG&E can each take to ensure reliability during unplanned outages.  Under one of these remedial actions schemes, PG&E pledged to, pursuant to a separate interruptible transmission agreement with the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from