Prolongation Claims: The Basic Principles

HKA Quantum Expert Craig Enderbury sets out the basic principles of prolongation cost claims using a simple and hypothetical example. He highlights the common

United StatesCorporate/Commercial Law

HKA Quantum Expert Craig Enderbury sets out the basic principles of prolongation cost claims using a simple and hypothetical example. He highlights the common pitfalls of assuming time equals money and the misguided application of rates and prices from preliminaries schedule of rates / bill of quantities.

A Contractor holds an internal monthly meeting on a construction project that is in delay and over budget. Someone remarks, "Let's get an extension of time, and then we can recover all our time-related costs", swiftly followed with an enthusiastic reply, "Sounds like a plan. We can adopt our tender rates for preliminaries items and multiply the rates by the period of over-run".

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from