Amending FIDIC Contracts — A Dozen Key Issues

This article examines some of the most commonly made amendments to the standard FIDIC Forms of Contract by both Employers/Owners and Contractors.

United StatesCorporate/Commercial Law

This article examines some of the most commonly made amendments to the standard FIDIC Forms of Contract by both Employers/Owners and Contractors. For this purpose, we have considered FIDIC's Silver and Yellow Books since these design and build contracts are the most commonly used forms of FIDIC Contract for major infrastructure and energy projects and are the pre-eminent form used in the Middle East and Africa.

In no particular order, Employers often seek to amend these FIDIC Contracts in the following ways:

1. The Silver and Yellow Books are both relatively light on warranties from the Contractor. Employers will often replace Clause 4.1 in both Silver and Yellow Books with a bespoke set of warranties. Whilst both Silver and Yellow Books provide a fitness for purpose warranty from the Contractor, further provisions are often added providing a design standard (notwithstanding the fitness for purpose obligation), adding warranties in relation to the use of prohibited

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from