PJM Makes MOPR Compliance Filing And Proposes Timing For Delayed RPM Auction

A&O Shearman
A&O Shearman
Contributor

A&O Shearman

Introducing A&O Shearman Unparalleled global depth for a changing world. Today more than ever,...

View firm profile
Explore more from A&O Shearman

On March 18, PJM Interconnection, L.L.C filed with the FERC proposed changes to its Tariff in compliance with FERC's order of December 19, 2019, which required PJM to expand, with certain exemptions and exceptions, ...

United StatesCompliance

Ohio Commission Requests Comment Delay for COVID-19 Emergency

On March 18, PJM Interconnection, L.L.C (PJM) filed with the Federal Energy Regulatory Commission (FERC) proposed changes to its Tariff1 in compliance with FERC's order of December 19, 2019,2 which required PJM to expand, with certain exemptions and exceptions, its current Minimum Offer Price Rule (MOPR)3 to address state-subsidized electric generation resources and their impact on PJM's capacity market, the Reliability Pricing Model (RPM).

PJM also proposed that the new date for the Base Residual Auction (BRA) for the 2022/23 delivery year be tied to the date of FERC's order on the Compliance Filing. However, the Public Utilities Commission of Ohio (the PUCO) has requested an extension of time to file comments or a protest in response to PJM's Compliance Filing due to its limited resources during the COVID-19 emergency.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from