ARTICLE · 05 MAY 2011

Planning Act 2008 Blog 237: 9865 Brig y Cwm Representations Published

Today’s entry reports on the publication of the representations made about the second Infrastructure Planning Commission application.

United KingdomGovernment, Public Sector

This is entry number 237, published on 3 May 2011, of a blog on the Planning Act 2008 infrastructure planning and authorisation regime. Click here for a link to the whole blog. If you would like to be notified when the blog is updated, with links sent by email, click here.

Today's entry reports on the publication of the representations made about the second Infrastructure Planning Commission application.

Since the Infrastructure Planning Commission (IPC) opened for applications on 1 March 2010, it has only accepted two: both for energy from waste projects, and both promoted by Covanta Energy.

The second application is for a plant that will be able to produce 77MW of electricity (so above the 50MW threshold that makes it a nationally significant infrastructure project). It is to be called Brig y Cwm and situated at Cwmbargoed near Merthyr Tydfil in Wales. Like many projects you will therefore find it with at least four names: Merthyr Tydfil, Cwmbargoed, Brig