ARTICLE · 07 OCTOBER 2009

Recovering Prolongation Costs: A Cautionary Tale

The recent TCC case of Costain v Haswell highlights the difficulties that may be faced when a party attempts to recover prolongation costs.

United KingdomFinance and Banking
Caroline Cummins
Caroline Cummins

The recent TCC case of Costain v Haswell highlights the difficulties that may be faced when a party attempts to recover prolongation costs.

Costain's case, in a nutshell, was that, due to negligence on the part of consulting engineer Haswell, the foundation designs for two new structures at a Water Treatment Works had to be changed at a late stage, causing Costain additional direct cost and also delay to those works, which were being undertaken by Costain on a design and build basis for United Utilities Water Ltd, along with numerous other structures on the same site.

Costain's allegations of negligence against Haswell were accepted by the judge after hearing the expert evidence, but in its claim for damages, in particular the recovery of the costs of prolongation of the works due to delay resulting from the need to redesign, failed for want of proof. Instead, Costain had to adopt its opponent's case on the effect of the delay, leading to a much diminished recovery.