What Should Be The Content Of The Notice Of Dissatisfaction Against DAB Decisions With Respect To The Disputes Arising From FIDIC Contracts?

The FIDIC contracts which we frequently encounter in international contracting, contain detailed regulations with regards to resolving the disputes that may arise under the projects.

TurkeyLitigation, Mediation & Arbitration

The FIDIC contracts which we frequently encounter in international contracting, contain detailed regulations with regards to resolving the disputes that may arise under the projects.

In situations where it is not excluded from the scope of application by the parties of project / contract, FIDIC stipulates a gradual / multi-tier resolution of disputes. In this sense, in case where the extension of time and/or additional payment claims (or any similar claims) of the Contractor causes a dispute between the parties of the contract, FIDIC regulations provide that the disputes shall primarily be resolved by the "dispute adjudication board", as commonly referred to as the DAB (or, in some cases, dispute board / DB). As a matter of fact, in cases where the DAB process is not excluded, the operation of this process constitutes a precondition (condition precedent) for the commencement of arbitration. In that sense, for instance, if a party resorts to arbitration without