Share on LinkedInShare on LinkedIn

ARTICLE · 18 NOVEMBER 2025

Regulatory Briefing: Contracted Capacity, Capacity Exceedance And System Use Charges Under EMRA Decision 13922

Kesikli Law Firm
Kesikli Law Firm
Contributor
Kesikli Law Firm

Kesikli Law Firm

Kesikli Law Firm, a leading law practice based in Istanbul, Turkey, serves a diverse client base,...

View firm profile
Explore more from Kesikli Law Firm

The Energy Market Regulatory Authority ("EMRA" or the "Authority") published its Board Decision dated 6 November 2025 and numbered 13922 in the Official Gazette...

TurkeyEnergy and Natural Resources

The Energy Market Regulatory Authority ("EMRA" or the "Authority") published its Board Decision dated 6 November 2025 and numbered 13922 in the Official Gazette No. 33074 on 11 November 2025, thereby putting the Decision into force.

The Decision, issued within the scope of Articles 7 and 14 of the Electricity Market Grid Connection and System Use Regulation, introduces a practical framework for evaluating capacity-increase applications of generation facilities, with particular emphasis on grid security, implementation periods, and the treatment of capacity exceedance.

A summary of the main provisions is outlined below.

Article 1/a – Application Process (Facilities Connected to the Transmission Grid)

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from