Electricity Market - Scope Of Capacity Mechanism And YEK-G Transition Period

The Regulation Amending the Electricity Market Capacity Mechanism Regulation and the Regulation Amending the Regulation on Renewable Energy Source Guarantee Certificate in Electricity Market published in...

TurkeyEnergy and Natural Resources

New developments

The Regulation Amending the Electricity Market Capacity Mechanism Regulation and the Regulation Amending the Regulation on Renewable Energy Source Guarantee Certificate in Electricity Market published in the Official Gazette on 21 May 2021, introduced significant changes to the capacity mechanism and renewable energy resource guarantee certificate ("YEK-G") applications.

What changes have been introduced?

1. The definition of facilities that can benefit from the capacity mechanism has been changed.

(i) Build-operate projects and (ii) power plants that are existing and in operation in accordance with their licenses, whose temporary acceptance date is more than 13 years (calculated starting from the provisional acceptance date of their oldest unit) and that are not based on domestic resources, both of which were previously not included in the capacity mechanism, can participate in the capacity mechanism.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from