Changes To The Licensing Process In The New Turkish Electricity Market Legislation

The new Electricity Market Law (the "New Law") that came into force on March 30, 2013 brought some changes to the licensing procedures, especially for the generation licenses.

TurkeyEnergy and Natural Resources

The new Electricity Market Law (the "New Law") that came into force on March 30, 2013 1 brought some changes to the licensing procedures, especially for the generation licenses. The most important is the introduction of a "preliminary license" procedure in place of the pre-construction phase; a period where the licensees are required to obtain the various permits for their construction and operation, but are banned from share transfers. The new licensing regulation2, drafted in accordance with the New Law, has further clarified the "preliminary license" procedure.

In the old system , generation licensees were provided a separate term for the pre-construction phase (22 to 30 months depending on the type of the power plant) and then the construction completion phase would follow (ranging from 18 to 72 months depending on the type of facility and installed capacity)3. These terms were incorporated into the license and if the licensee was unable to start or complete

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from