As the construction industry continues to develop in Tanzania,
the use of international standard contracts has increased. In
particular, we have seen the FIDIC (Fédération
Internationale Des Ingénieurs-Conseils) standard form
contracts used more frequently in this jurisdiction.
It is standard practice for most construction contracts,
including FIDIC contracts, to contain a liquidated damages clause.
As liquidated damages (LDs) provide for a
pre-agreed rate of damages, payable to the employer by the
contractor in the event of a contractor's delay in performing
the work, the risk of delay for the employer is mitigated.
LDs, as opposed to general damages, do not require the claimant
to prove that the losses claimed have actually been suffered. As
such, the contract will provide for a genuine and fixed
pre-agreed estimate of loss. Often this is calculated based
on the amount of loss that will be incurred on a daily basis if the
work is not completed on time.