In Kunene Rampala Inc
Attorneys (“KR
Inc”) v North West Province Department of
Education and Sport and Development (“the
Department”), the Supreme Court of Appeal (the
"SCA") reviewed a High Court decision
which invalidated a contract addendum for failing to follow public
procurement prescripts.
Background
Following a successful tender bid, a Service Level Agreement was
concluded by the parties to provide services for evaluations,
adjudications and supply chain management administration in the
provision and delivery of the Learner Teacher Support Material
(“LTSM”). The contracted price was
ZAR1 243 215.60 and would be valid for 12 months.
Three days after the agreement was concluded and before KR Inc.
began any work, the parties concluded an addendum to the agreement
without following proper procurement processes. The addendum stated
that in addition to the work that KR Inc. had to perform in terms
of the agreement, they were further tasked with providing