ARTICLE · 12 DECEMBER 2019

Can You Contractually Exclude The Unconscionability Exception, In The Context Of A Performance Bond, In A Separate Document?

In the recent decision of Bintai Kindenko Pte Ltd v Samsung C&T Corp [2019] SGCA 39, the CA upheld a contractual exclusion clause.

SingaporeCorporate/Commercial Law

In the recent decision of Bintai Kindenko Pte Ltd v Samsung C&T Corp [2019] SGCA 39, the CA upheld a contractual exclusion clause that excluded the right of a subcontractor to rely on the unconscionability exception to prevent the main contractor from calling on the performance guarantee.

The respondent main contractor was appointed by the Employer for a project to upgrade the Suntec City Convention Center. The appellant was then appointed as the project's M&E subcontractor under a Letter of Acceptance dated 3 December 2012 ("LOA"). Pursuant to the LOA, the subcontractor provided a banker's guarantee ("BG"), which was payable on demand in writing.

Disputes arose as to whether the subcontractor was liable for delays in its work between March 2014 and December 2015. On 27 January 2016, the main contractor rejected all of the subcontractor's requests for extension of time and computed the delays in the subcontract works. However, it did not raise any claim for