Article
Liabilities Under Pre-Construction Services Agreements
The Technology and Construction Court recently ruled that liabilities from a Pre-Construction Services Agreement can survive entry into a main JCT contract, even when the PCSA is "subsumed into and subject to" the subsequent agreement. This decision clarifies how pre-existing contractual breaches may continue to affect extension of time claims and contractor obligations under main construction contracts.

Womble Bond Dickinson (UK) LLP