ARTICLE · 15 FEBRUARY 2024

Significant Changes Envisaged To Grid Connection For New Power-Generation Capacities In Romania

The Romanian Energy Regulatory Authority ("ANRE") has announced important amendments to the rules for connecting new power-generation capacities to the public network.

RomaniaEnergy and Natural Resources

February 2024 – The Romanian Energy Regulatory Authority ("ANRE") has announced important amendments to the rules for connecting new power-generation capacities to the public network.

On 1 February 2024, ANRE released for public consultation a draft order ("Draft Order") regarding the approval of the Methodology for capacity allocation of new power-generation capacities (the "Methodology") as well as other amendments to ANRE Order no. 59/2013 approving the public grid connection regulation (the "Connection Regulation"). Comments to the Draft Order may be submitted to ANRE by 1 March 2024.

The main changes introduced under the Draft Order concern (i) a change of the grid connection process applicable to power-generation capacities above 1 MW by allocating the capacity based on a tender, and (ii) the introduction of a financial guarantee to be set up prior to the issuance of a grid connection permit ("ATR"), with a fixed percentage of 5% of the value of the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from