On 26 February 2025, the Ministry of Housing and Spatial
Planning published a revised version of the UAC 2012, removing
sections 1 and 2 of paragraph 12 (Contractor's Liability
After Delivery). This unilateral amendment brings the UAC 2012 into
alignment with the statutory regime on hidden defects introduced by
recent legislation: contractors are now liable for defects not
discovered at the time of delivery, unless they can prove that
these defects are not attributable to them.
Amendment UAC 2012
In construction agreements, it is common practice to declare
general terms and conditions applicable. In the Dutch building
practice, one of the most widely used sets of such conditions is
the Uniform Administrative Conditions for the Execution of Works
and Technical Installation Works 2012 (UAC 2012).