ARTICLE · 13 MAY 2025

Clarity For The Construction Sector: UAC 2012 Aligned With The Dutch Quality Assurance Act

Loyens & Loeff
Loyens & Loeff
Contributor
Loyens & Loeff

Loyens & Loeff

One firm: Law and Tax Loyens & Loeff is a leading independent, full-service law and tax firm in...

View firm profile
Explore more from Loyens & Loeff

On 26 February 2025, the Ministry of Housing and Spatial Planning published a revised version of the UAC 2012, removing sections 1 and 2 of paragraph 12...

NetherlandsReal Estate and Construction

On 26 February 2025, the Ministry of Housing and Spatial Planning published a revised version of the UAC 2012, removing sections 1 and 2 of paragraph 12 (Contractor's Liability After Delivery). This unilateral amendment brings the UAC 2012 into alignment with the statutory regime on hidden defects introduced by recent legislation: contractors are now liable for defects not discovered at the time of delivery, unless they can prove that these defects are not attributable to them.

Amendment UAC 2012

In construction agreements, it is common practice to declare general terms and conditions applicable. In the Dutch building practice, one of the most widely used sets of such conditions is the Uniform Administrative Conditions for the Execution of Works and Technical Installation Works 2012 (UAC 2012).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from