Share on LinkedInShare on LinkedIn

ARTICLE · 16 APRIL 2024

Porthos Allowed To Proceed: A Relief For Energy Transition

Since September 2021, the energy transition (and the Netherlands as a whole) has been waiting for the irrevocability of the permits for Porthos.

NetherlandsEnergy and Natural Resources

Since September 2021, the energy transition (and the Netherlands as a whole) has been waiting for the irrevocability of the permits for Porthos. In November 2022, the (Administrative Law Division of the) Council of State came out with a ruling, but this was only an interim ruling and looked more at the so-called 'partial building exemption' than at Porthos. Today, almost two years after the underlying permits were adopted, the Council of State has come out with a final ruling.

Fortunately, the Council of State ruled that the permissions granted for Porthos can be upheld. The project may go ahead with the necessary delay and can thus make a necessary contribution to the Dutch climate goals.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from