The ICC tribunal’s final award in Refinería Madero Tamaulipas, S.A.P.I. de C.V. v. Pemex Transformación Industrial is a useful decision for anyone drafting or litigating arbitration clauses in State-linked infrastructure contracts. At its core, the award answers a deceptively simple question: when a public works contract excludes disputes over early termination from arbitration, does that exclusion also bar arbitration over a later, bilateral settlement of amounts due? The tribunal’s majority said no.1
The Dispute
Refinería Madero and Pemex Tri entered into a public works contract for engineering, procurement, supply, installation, construction, testing and commissioning works at the Francisco I. Madero refinery in Tamaulipas, Mexico.2 The contract contained an ICC arbitration clause seated in Mexico City, governed by Mexican federal law, but expressly excluded administrative rescission and early termination from arbitration.3 Pemex Tri later early-terminated the contract. The