Share on LinkedInShare on LinkedIn

ARTICLE · 27 JUNE 2024

Contracts Of Work And The Burden Of Proof

In the case Aretrop Limited (C49725) (the "Claimant Company") vs Foundation for Tomorrow's Schools (the "Foundation") & the Hon. Dr. Justyne Caruana in her capacity as Education Minister (the "Hon. Minister")...

MaltaCorporate/Commercial Law

Introduction

In the case Aretrop Limited (C49725) (the "Claimant Company") vs Foundation for Tomorrow's Schools (the "Foundation") & the Hon. Dr. Justyne Caruana in her capacity as Education Minister (the "Hon. Minister"), the Hon. Madame Justice Audrey Demicoli delved into and examined various contracts entered into between the parties for works carried out by the Claimant Company, including the delivery of specialised furniture in various schools around Malta and Gozo. This case was decided by the First Hall Civil Court (the "FHCC") on the 6 June 2024.

The claimant company requested the FHCC (i) to determine whether the defendants or any of them were debtors of the Claimant Company for works carried out by the Claimant Company on the instructions of the defendants (ii) to liquidate the amount owed to the Claimant Company and (iii) order the defendants to pay the amount as liquidated.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from