ARTICLE · 22 NOVEMBER 2024

Racing The Clock: Liquidated Ascertained Damages Claims Revisited In The Wake Of The Obata-Ambak Holdings Case

On 29.7.2024, the Federal Court heard and decided on the case of Obata-Ambak Holdings Sdn Bhd v Prema Bonanza Sdn Bhd & Other Appeals [2024] CLJU 1657. While this case might be understood as a mere...

MalaysiaReal Estate and Construction

On 29.7.2024, the Federal Court heard and decided on the case of Obata-Ambak Holdings Sdn Bhd v Prema Bonanza Sdn Bhd & Other Appeals [2024] CLJU 1657. While this case might be understood as a mere case of Liquidated Ascertained Damages ("LAD") claim, this case serves a huge importance to the housing industry, as this LAD claim arose after the Federal's Court decision in Ang Min Lee & Ors v. Menteri Kesejahteraan Bandar, Perumahan dan Kerajaan Tempatan & Anor and Other Appeals [2020] 1 CLJ 162; [2020] 1 MLJ 281.

Ang Min Lee: Nullifying the Controller's Power to Grant EOT to House Developers

In the case of Ang Min Lee which was decided on 26.11.2019, the Federal Court heard a judicial review by the purchasers who had not been compensated with LAD after the developer was granted an extension of time ("EOT") by the Minister, after the Housing Controller ("Controller") initially declined the EOT request.