In Jaks Island Circle Sdn Bhd v Star Media Group Bhd and Another (Originating Summons No. WA-24C(ARB)-11-02/2018), ...

MalaysiaLitigation, Mediation & Arbitration

In Jaks Island Circle Sdn Bhd v Star Media Group Bhd and Another (Originating Summons No. WA-24C(ARB)-11-02/2018), the Malaysian High Court considered whether an inquiry of damages arising out of an undertaking by an applicant to pay damages for an injunction wrongly granted by a court in support of arbitration proceedings should await the outcome of a pending arbitration between the parties.

Background

In February 2018, the plaintiff ("Jaks Island") commenced two separate actions against Star Media Group Bhd ("Star Media") to restrain the latter from receiving payments under two bank guarantees in the sum of RM25 million each ("Bank Guarantees"). To obtain the injunctions, Jaks Island undertook to pay damages to Star Media arising in the event the injunctions were wrongly granted. The High Court granted Jaks Island temporary injunctions pending the resolution of the actions in the High Court.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from