Compensation For Late Delivery Of New Apartments

It should be noted that clauses of this nature are common and appear in almost every sale contract from a contractor.

IsraelReal Estate and Construction
Ariel Nadler
Ariel Nadler

Developers can no longer rely on changes to an apartment, requested by the purchaser, as reason to avoid payment of compensation for late delivery. This was ruled recently by the Supreme Court in a case involving a dispute between purchasers of an apartment and a contracting company.

The Sale (Apartments) Law states that a delay of over 60 days from the date specified in the sale contract for the delivery of the apartment to the purchaser, means that the purchaser will be entitled to compensation without proof of damage, and this from the first day of delay.

In the abovementioned case, the sale contract which was signed by the purchasers and the contracting company stated that any request to change or supplement the apartment will postpone the delivery date of the apartment for at least 60 days.