Amendment 3A To NOP 38

It has been over a decade since the National Outline Plan (NOP) 38 in the matter of building reinforcements from earthquakes, was first approved.

IsraelReal Estate and Construction
Efraim Weinstein Law Offices
Efraim Weinstein Law Offices

Background and purpose of the amendment

It has been over a decade since the National Outline Plan (NOP) 38 in the matter of building reinforcements from earthquakes, was first approved. One of the substantial amendments to the provisions of NOP 38, is the second amendment approved in 2010 which added demolition and construction provisions to the plan, under the framework of an NOP 38 project ("NOP 38/2").

Throughout actual implementation of the provisions of NOP 38/2, it transpired that the calculation of rights under the NOP 38/2 format, is not clear enough, and is open to different interpretations, leading to two entirely different main calculation methods regarding the scope of building rights provided under the provisions of NOP 38/2.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from