ARTICLE · 27 NOVEMBER 2023

Indicative Roadmap For Ireland's Next Offshore Wind Auction Published

William Fry LLP
William Fry LLP
Contributor
William Fry LLP

William Fry LLP

William Fry advises leading Irish and international companies, covering both the public and private...

View firm profile
Explore more from William Fry LLP

This builds on the momentum from Ireland's successful first offshore renewable electricity subsidy scheme auction round (ORESS 1) in May.

IrelandTransport

The Government's cross-departmental Offshore Wind Delivery Taskforce has published its "indicative roadmap" towards the State's next offshore wind auction (ORESS 2.1).

This builds on the momentum from Ireland's successful first offshore renewable electricity subsidy scheme auction round (ORESS 1) in May. Roughly 3GW of offshore wind generation capacity was awarded under ORESS 1 in what was a breakthrough moment for the country's offshore wind market. This was comprised of circa 2.6GW off the east coast and 450MW off the west coast of Ireland.

Location & Quantity

ORESS 2.1 will procure up to 900MW of offshore wind generation capacity from a State-selected provisional designated area, known as a Designated Maritime Area Plan (DMAP), located off the south coast of Ireland (the South Coast DMAP). The South Coast DMAP will represent Ireland's first step into the plan-led development phase of the country's offshore potential. It will act as a management plan and

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from