ARTICLE · 11 AUGUST 2023

RESS 3 Update: Provisional Qualification Decision & Revised RESS 3 Terms & Conditions

William Fry LLP
William Fry LLP
Contributor
William Fry LLP

William Fry LLP

William Fry advises leading Irish and international companies, covering both the public and private...

View firm profile
Explore more from William Fry LLP

The final qualification decision date is scheduled for 1 September 2023, with bidding opening on 8 September 2023 and final auction results anticipated on 9 October 2023.

IrelandEnvironment

Today marks an important date for prospective bidders in the third onshore auction under the Renewable Electricity Support Scheme (RESS 3), as the Government publishes its provisional qualification decision on a member private basis via the RESS Auction Platform.

The final qualification decision date is scheduled for 1 September 2023, with bidding opening on 8 September 2023 and final auction results anticipated on 9 October 2023.

RESS 3 – a Recap

The Renewable Electricity Support Scheme (RESS) is an auction-based scheme which invites renewable electricity projects to bid for capacity and receive a guaranteed price for the renewable electricity they generate. RESS 3 will be the third onshore auction run by the government to procure renewable generation capacity for the Irish electricity system and is a key pillar of the Government's drive to meet its environmental commitments under the Climate Action Plan 2023.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from