Environmental Protection Agency In Court Against Landfill Companies, Their Lender Bank And Receiver Seeking Payment Of Landfill Closure And Restoration Costs

Operators of landfill sites are obliged to charge fees for disposal of waste which must be sufficient to cover.

IrelandEnvironment
  1. Closure, Restoration, Remediation and Aftercare Costs – the law

Operators of landfill sites are obliged to charge fees for disposal of waste ("gate fees") which must be sufficient to cover:

  • The total costs of running the landfill; and
  • The estimated costs for the clean-up, restoration, remediation and aftercare of the landfill, (the "closure and restoration costs"), after the landfill has closed. 

The EPA may refuse to grant a landfill licence if the landfill operator does not provide for the collection of sufficient fees to cover these costs.  The landfill licensee must report annually to the EPA on its fees to demonstrate that the fees are sufficient for this purpose. 