ARTICLE · 29 MAY 2025

Key Takeaways From PLN's 2025-2034 Electricity Supply Business Plan

A&O Shearman
A&O Shearman
Contributor

A&O Shearman

Introducing A&O Shearman Unparalleled global depth for a changing world. Today more than ever,...

View firm profile
Explore more from A&O Shearman

On May 26, 2025, Indonesia's minister of energy and mineral resources (MEMR) held a press conference themed "Increasing Security and Sustainability of National Energy"...

IndonesiaEnergy and Natural Resources

On May 26, 2025, Indonesia's minister of energy and mineral resources (MEMR) held a press conference themed "Increasing Security and Sustainability of National Energy" to announce the launch of PLN's 2025-2034 Electricity Supply Business Plan (RUPTL).

While the full text of the new RUPTL has not yet been publicly released, the following is a summary of the key points shared during the press conference.

Power generation targets

PLN outlined ambitious targets for the expansion of power generation capacity from various energy sources within the next ten years, including, among others:

Solar PV: Target of 17.1 GW for 2025-2034.

Our preliminary commentary: Achieving this will require significant land acquisition (approximately 1 hectare per 1 MW for ground-mounted installations). Floating solar PV is also being considered, with potential to utilize up to 20% of surface water areas, subject to government approval for a higher allocation. Spatial planning needs

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from