I. Introduction
The Hon'ble Supreme Court in C & C Constructions
Ltd. v. IRCON International Ltd.1 The issue was
that ground challenging an arbitral award had not been raised for
the first time before the High Court Division Bench under Section
37 of the Arbitration and Conciliation Act
("Act").
The crux of the dispute between the parties was whether Clause
49.5 of the General Conditions of Contract
("GCC") of their Contract, which
prohibited the contractor from claiming damages or compensation for
delays attributable to the employer, was enforceable, and whether
the Appellant (C & C Constructions Ltd.) could claim damages
despite agreeing to extensions of time without penalties.