Recently, in the case of Vivek Khanna vs. OYO
Apartments Investments LLP1, the
Delhi High Court dismissed a petition filed under Section 34 of the
Arbitration and Conciliation Act, 1996 (“A&C
Act“), by way of which, Mr. Vivek Khanna (the
“Petitioner“) assailed the award dated
March 31, 2023 (the
“Impugned Award“)
passed by the arbitral tribunal comprising of a sole
arbitrator.
The Petitioner and OYO Apartments Investments LLP (the
“Respondent“) had executed a lease
agreement dated February 18, 2019
(“Agreement“), under the terms of
which, the Petitioner had leased out his premises to the Respondent
for a term of 60 months, with a lock-in period of 36 months, during
which, neither party could terminate the lease. The Agreement
casted an obligation on the Respondent to pay a minimum guaranteed
amount of Rs. 2,90,000/- or net revenue share, whichever is higher,
payable every lease month, w.e.f. June 1, 2019. However, for the
first two months, the Respondent was