ELP Arbitration Update - Supreme Court Sets Timer For Disposal Of Pending Applications Under Section 11 Of The Arbitration Act

In Shree Vishnu Constructions, the Supreme Court observed that the impugned judgement was passed by the High Court for the State of Telangana in an application under section 11 of the Arbitration and Conciliation Act, 1996 ...

IndiaLitigation, Mediation & Arbitration

SUPREME COURT SETS THE TIMER FOR DISPOSAL OF PENDING APPLICATIONS UNDER SECTION 11 OF THE ARBITRATION ACT : IF APPLICATIONS UNDER SECTION 11(5) AND 11(6) OF THE ARBTIRATION ACT HAVE BEEN PENDING FOR MORE THAN ONE YEAR, THE HIGH COURTS ARE TO ENSURE THAT SUCH APPLICATIONS ARE DECIDED WITHIN SIX MONTHS.

SHREE VISHNU CONSTRUCTIONS V. THE ENGINEER IN CHIEF MILITARY ENGINEERING SERVICE & ORS.1

Background:

In Shree Vishnu Constructions, the Supreme Court observed that the impugned judgement was passed by the High Court for the State of Telangana (High Court) in an application under section 112 of the Arbitration and Conciliation Act, 1996 (the Act) after a period of 4 years from the date of filing3.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from