KIPL Vistacore Infra Projects JV v. Municipal Corporation of the City of Ichalkarnji...

IndiaLitigation, Mediation & Arbitration

KIPL Vistacore Infra Projects JV v. Municipal Corporation of the City of Ichalkarnji

Bombay High Court | MANU/MH/0513/2024

Background facts

  • The Municipal Corporation of Ichalkarnji (Respondent) proposed construction of a project for 2 sewage treatment plants under the Urban Infrastructure Development Scheme for Small and Medium Towns Scheme Mission (UIDSSMT), funded by the Government of India and the State of Maharashtra. Pursuant to the tender floated by the Respondent in 2021, the bid of KIPL Vistacore Projects JV (Petitioner) was accepted and the Work Order was issued in its favor.
  • By the year 2019, the Petitioner claimed to have completed 55% of work and the delay was attributed to the Respondent as the possession of the land was handed over belatedly along with the drawings for Sewage Treatment Plants (STP).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from