The present appeal in the matter of Mohan Lal Fatehpuria v. M/s Bharat Textiles & Ors. 1 arose from the order dated 22.04.2025 passed by the Hon’ble High Court of Delhi, whereby the Court declined the request for substitution of the Sole Arbitrator but granted an extension of four months to complete the arbitral proceedings under Section 29A (6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the “Act”).
The Appellants, along with Respondent Nos. 2 to 4, were parties to a Partnership Deed dated 18.05.1992, which contained an arbitration clause governing disputes between the partners. Subsequently, M/s Bharat Textiles was formally registered as a partnership firm on 05.01.2007 and business operations were carried out under the said arrangement. Disputes later arose between the parties concerning the affairs of the firm, leading the Appellants to invoke the arbitration clause.