Aneja Constructions (India) Ltd V. Grim-Tech Projects (I) Pvt Ltd & Ors

Aneja Constructions (India) Ltd (ACIL) and Grim-Tech Projects (I) Pvt Ltd (GTPL) had executed principal work order on March 07, 2013 for carrying out pile foundation at Muzaffarpur Thermal Power Plant...

IndiaLitigation, Mediation & Arbitration

Delhi High Court | OMP (COMM) 464/2019

HSA Viewpoint

The judgment demonstrates the need for supporting evidence to claim losses suffered due to overstay at the site. The good practice remains to have the supporting evidence for Tribunal's appreciation.

Background facts

  • Aneja Constructions (India) Ltd (ACIL) and Grim-Tech Projects (I) Pvt Ltd (GTPL) had executed principal work order on March 07, 2013 for carrying out pile foundation at Muzaffarpur Thermal Power Plant of Kanti Bijlee Utpadan Nigam Ltd. The respective work order was amended on July 24, 2013.
  • GTPL had submitted bills for INR 2,94,55,392 and claimed that an amount of INR 1,00,07,985 was due and payable by ACIL. ACIL had acknowledged that INR 1,00,07,985 was due to GTPL. GTPL also claimed that its equipment which was to be used for piling work were lying idle for almost 2 years and could have been deployed at other sites. Accordingly, GTPL also sought compensation for overstay of the equipment

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from