According to an amendment to the Hungarian Corporate Income Tax
Act approved in July 2018, taxpayers may be eligible for higher tax
allowance in connection with an investment project to comply with
energy efficiency targets, upon placing the project into operation,
in the tax year following the year when the project was placed into
operation – or in the same tax year at the taxpayer's
discretion – and in the following five tax years.
The tax allowance claimed by the taxpayer for any investment
project may be 30-45%, subject to the location of the investment
project, and it may be increased by 20 percentage points for aid
granted to small companies and by 10 percentage points for aid
granted to medium-sized companies. However, the amount of the tax
allowance may not exceed the forint equivalent of 15 million
euros.