Only a few years ago, the Hungarian National Energy Strategy set the then ambitious target of reaching 6 GW of solar power capacity by 2030.

HungaryEnergy and Natural Resources

Only a few years ago, the Hungarian National Energy Strategy set the then ambitious target of reaching 6 GW of solar power capacity by 2030. By early 2024, that target had already been achieved, as the gross capacity of PV installations doubled within only two years. The new target for 2030 is now set at 12 GW, and there is little doubt that it will be easily reached.

The joy of the Hungarian energy policymakers is matched by the sorrow of many investors. The government's latest decision in this area (Government Decree 54/2024 (III.6.)) practically eliminated the possibility for any new renewable energy projects (with very limited exceptions) to receive a grid connection with feed-in-capacity. This came short after the launch of the second round of the recently revised grid connection allocation procedure, where the developers submitted capacity applications in the magnitude exceeding 10 GW. Unfortunately for many, as the grid connection rights required to install the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.