ARTICLE · 15 OCTOBER 2002

Denying Access to Site

Hong KongReal Estate and Construction

The decision of the English Court of Appeal in March 2002 in Hayes v. Stewart highlights the dangers to employers of denying contractors access to site.

The facts

Ms. Hayes was employed by Mr. Stewart to supply and fit windows to a property. The conditions of contract were set out on the back of Hayes’s standard order form. They provided that times quoted for delivery and installation were quoted in good faith and that work normally took between four to ten weeks.

Mr. Stewart had not read the conditions. He claimed that it was a condition of the contract that work would be completed within one week.

Work began on 22 November 1999 and was not completed within one week. There were some discussions between the parties and Ms. Hayes’s fitter attended the property on 30 November to remedy some defects. There was still work to be done and, whilst Ms. Hayes proposed that the fitter should return on 3 December to complete, Mr. Stewart insisted that she was now out of time.