An important judgement was recently delivered by Akenhead J in the Technology and Construction Court in London.

Hong KongReal Estate and Construction

An important judgement was recently delivered by Akenhead J in the Technology and Construction Court in London in the case of Walter Lilly and Company Limited v Giles Patrick Cyril Mackay (and Another).

Background

The judgement was delivered on 11 July 2012 and is over 200 pages long. It covers a range of issues arising out of a construction project in London that went badly wrong. While the facts of the case are complex, suffice to say that the case involved the usual disputes between an Employer and Contractor in respect of claims for late completion and defective work on the one hand and claims for extensions of time and loss and expense on the other.

Akenhead J took the opportunity to review the authorities on a number of issues in his judgement but the three matters referred to in the heading of this Alert are of particular interest. They will be dealt with briefly in turn below.