Construction companies entering into joint venture (JV)
contracts should be cautious of entering into agreements where the
responsibility for, and timing of cost overruns is not tightly
specified, to avoid unexpected surprises.
In Doosan Enpure Limited v. Interserve Construction Limited
[2019] EWHC 2497 (TCC), Mrs. Justice Jefford made obiter
comments that should cause parties to reflect on their obligations
under contracts under the NEC3 Option C contract.
Follow the formula
Doosan Enpure Ltd. (Doosan) entered into a joint venture
agreement (JVA) with Interserve Construction Ltd. (Interserve) for
the purpose of carrying out upgrade works at a treatment plant
operated by Northumbrian Water under the NEC3 form with Option C
(NEC3).