In its ruling of September 30, 2013 (7 U 32/13) the OLG Cologne has found that an incorrect approval planning does not have a relevant impact on the implementation planning.

GermanyReal Estate and Construction
Ralf-Thomas Wittmann
Ralf-Thomas Wittmann

I. Private Building Law – Liability of the architect -: No joint and several liability without a causal contribution – Implementation planning deviating from approval planning

In its ruling of September 30, 2013 (7 U 32/13) the OLG Cologne has found that an incorrect approval planning does not have a relevant impact on the implementation planning.

The client commissioned architect A with the approval planning for, amongst other things, an underground car park, a further architect B with the implementation planning and a general contractor C with the turnkey construction.

Incorrect approval planning

In the context of independent proceedings for the taking of evidence initiated by the client it became clear that according to the expert the approval planning was incorrect, because the tractrix curve as well as the ramp of the underground car park did not comply with the Car Park Ordinance of North-Rhine Westphalia (GarVO-NW). The approval planning intended a