Notice Of Claims For Daily Penalties

Bech-Bruun
Bech-Bruun
Contributor
Bech-Bruun

Bech-Bruun

Overview Bech-Bruun is a leading full-service law firm with global reach, advising clients in the...

View firm profile
Explore more from Bech-Bruun

Under Danish construction law, daily penalties serve as contractual remedies for contractor delays, but employers must meet strict formal requirements to enforce them. Recent arbitration decisions reveal that even when contractors are responsible for delays, failure to properly document the delay or provide timely notice can result in the complete loss of penalty claims. What procedural safeguards must employers implement to preserve their right to daily penalties under AB18?

DenmarkReal Estate and Construction

A recent arbitration award confirms the well-established rule that an employer forfeits its claim for daily penalties if it fails to give notice within reasonable time. At the same time, the award raises the question of how early the employer must react to an anticipated delay under the General Conditions for Building and Construction Works and Supplies (AB18).

Daily penalties constitute key contractual remedies for delays attributable to the contractor. In particular, daily penalties enable the employer to recover without proving a particular financial loss and may serve as an incentive for the contractor to accelerate performance. However, entitlement to daily penalties is conditional upon compliance with both the agreement and the subsequent formal requirements.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from