The Fourth Generation (4G) road concessions were planned by the
Colombian government as a response to the dramatic lack of adequate
transport infrastructure in the country, and aligned with the goals
set forth in the National Development Plan. This megaproject has
allowed the government to put into practice its lessons learned
during the last two decades in the contracting processes for
infrastructure projects and toll road concessions in
particular.
Among other flaws of previous
generations of concession projects, the government had to pay
substantive down payments regardless of the concessionaires'
compliance with service standards; the investors' capital
contributions were low; and the conflict resolution criteria and
mechanisms were unclear. In these prior projects, the State ended
up assuming most of the risk as problems arose with environmental
permitting, real estate purchases, and land use, among other
issues.