ARTICLE · 08 NOVEMBER 2019

Think Leaving Equipment On Site Extends Your Lien Period? Think Again

Builders' liens provide unpaid contractors and subcontractors on a construction project the ability to secure a debt claim against a piece of land

CanadaReal Estate and Construction

Builders' liens provide unpaid contractors and subcontractors on a construction project the ability to secure a debt claim against a piece of land. While courts have acknowledged that the purpose of builders' liens is to provide this protection, there are criteria that need to be met for a lien to be valid.

One such criterion is that a lien must be registered within a specific timeframe. While section 41 of the Builders' Lien Act (the "BLA") provides a 45 day deadline (90 days for an oil or gas well or an oil or gas well site) for lien registration after materials or services are last provided or a contract is abandoned, when this deadline commences can be unclear.

Equipment left on site, without more, will not extend a lien period

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from