The Owner Strikes Back: Subcontractor Unjust Enrichment Claims

This matter related to a construction project to replace a bridge. HPN Engineering was the general contractor. It retained the plaintiff, Central Welding and Iron Works...

CanadaReal Estate and Construction

When striking pleadings, the moving party must show that it is "plain, obvious, and beyond doubt" that the plaintiff's claim could not succeed – it must have no reasonable prospect of success. This is typically a high bar to meet. However, when a subcontractor advances claims against the federal Crown as owner for unpaid construction work, do such claims have a reasonable prospect of success? An Ontario court considered this issue, and ultimately struck the plaintiff's claims against the Crown.

Background

This matter related to a construction project to replace a bridge. HPN Engineering was the general contractor. It retained the plaintiff, Central Welding and Iron Works, as structural steel subcontractor. HPN provided partial payment to Central for its completed work. The owner, Public Works and Government Services Canada, a federal Crown corporation, failed to certify substantial performance of the project or of Central's subcontract with HPN. As such, HPN

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from